Crushed Stone Calculator
Measure each area in feet, enter the finished depth your project calls for, and get crushed stone in cubic yards and tons — with the compaction allowance for a finished base shown as its own line, never silently baked in.
Enter at least one area and a depth to see how much crushed stone to order.
How this is calculated
- Shape areas are summed and multiplied by the finished depth:volume = total area × depth (at depth d inches,cubic yards = square feet × d ÷ 324).
- For a compacted base, the loose volume to order isfinished volume × (1 + 36–47 %) — the measured compacted-to-loose expansion for ¾-inch dense graded base, shown as its own line.
- Tonnage = finished volume × 1.75–2.1 tons per cubic yard (compacted in place) — shown as a range because the conversion genuinely varies by quarry; in loose-fill mode the factor is discounted by the measured expansion instead.
Data used, with sources
| Value | Used as | Source |
|---|---|---|
| Tonnage conversion 1.75–2.1 tons/cu yd (compacted) | tonnage shown as a range — WisDOT statewide conversion factor for Dense Graded Base ¾-inch ("crusher run"-type graded base with fines), compacted in place; WHRP field measurements for the same class ran 1.80–1.86 tons/yd³, which is where the default sits. Clean open-graded stone (#57) runs lighter. Your supplier’s conversion governs. | Wisconsin Department of Transportation / Wisconsin Highway Research Program |
| Compaction: +36–47 % loose over finished volume | compaction allowance, shown as its own result line in compacted-base mode | Wisconsin Department of Transportation / Wisconsin Highway Research Program |
WHRP-measured compacted→loose expansion for Dense Graded Base ¾-inch is 36–47 %: a load of loose material shrinks by that much when compacted to a finished base, so ordering loose volume for a compacted project needs the extra. Skip it for loose decorative fill.
Why compaction is its own line
Most calculators quietly inflate their result by some fudge factor — or worse, ignore compaction entirely and leave you a third short on a driveway base. This one shows the correction separately, at the measured 36–47 %, so you can see what you are paying for and drop it when it does not apply (decorative fill, French-drain stone, anything left loose).
Choosing a finished depth
This page deliberately has no depth preset. Base thickness is an engineering judgment that depends on your soil, expected traffic, and frost — a number that honestly cannot be generalized from a calculator page. Use the depth from your project plan, paver manufacturer's spec, or contractor; if a structure rides on it, that spec — not this estimate — governs.
Frequently asked questions
How much does a cubic yard of crushed stone weigh?
What is crusher run (dense graded base)?
Why is there no recommended depth on this page?
Do I have to account for compaction when ordering?
Related calculators
Sources
- Weight-Volume Relationships and Conversion Factors for Soils and Aggregates of Wisconsin (WHRP G22-05) — Wisconsin Department of Transportation / Wisconsin Highway Research Program, accessed 2026-07-31.
Quantities on this page are planning estimates, not engineering advice or a purchase guarantee — product sizes vary by producer, so confirm coverage with your supplier before ordering.A load-bearing base under a structure is an engineering matter — follow your local code and project specification.